- More finances coming in, including over £1000 from our recent bag packing.
- Lift is fully installed and under test.
- Main hall walls and ceiling going well - on track for completion (or very nearly) this year.
- Lighting and alarm/fire alarm cabling and fittings for the main hall also going well.
- Dry store walls (1 sheet) and ceiling (2 sheets) now fully plasterboarded - 2nd sheet on the walls will hopefully be completed this week.
- Rubbish disposal and general tidying the site to facilitate further progress.
In the meantime, here are some pictures from the last few days.
Boarding out the end of the main hall |
Plasterboard on the ceiling and starting one gable end with insulation |
The other gable end getting Sterling board over the insulation, ready for plasterboard |
Finishing the staining of the T'n'G for upstairs |
![]() |
Lift doors in place (and locked pending testing) |